Costs and pricing
Part of Planning CRM costs with dated quotes, full labour and a separate ROI ledger
How to review a small business CRM quote
Small business CRM cost guide to reviewing dated supplier quotes, recording labour and VAT separately, and mapping invoice timing before a purchase decision.
| Case | Licence and usage, excluding VAT | Implementation, excluding VAT | Internal labour | Contingency and exit | Cost excluding VAT | VAT at 20% | Gross supplier cash |
|---|---|---|---|---|---|---|---|
| Low | £2,400 | £1,000 | £700 (20 hours) | £300 | £4,400 | £680 | £4,080 |
| Working | £4,800 | £3,000 | £1,400 (40 hours) | £900 | £10,100 | £1,560 | £9,360 |
| High | £8,400 | £7,000 | £2,800 (80 hours) | £2,000 | £20,200 | £3,080 | £18,480 |
For a small business CRM review, the opening figures are illustrative totals for a five-seat firm over 12 months, not a supplier quote or a reproducible estimate: the licence and usage inputs and loaded hourly rate are not specified. Use them only to see how separate cost, VAT and cash lines are presented; replace every figure with information from a dated quote and your organisation's approved labour rate before making a decision.
Set a fair boundary for every quote
Start with a dated supplier quote and compare every option over the same period, in one currency and on one tax basis.
Include the current manual process as a baseline. There is no typical CRM price: seats, limits, usage, implementation work and exit needs vary, so a headline figure alone cannot represent your cost.
Record the supplier's legal entity, product, edition, quote date and expiry, as well as the billing cycle, commitment term and renewal notice. Keep the total committed amount visible beside any monthly equivalent. An annual commitment expressed as a monthly figure is not the same as monthly billing.
Capture the quote exactly
- Supplier legal entity and product
- Edition, quote date and expiry
- Currency, VAT presentation, billing cycle
- Commitment term, renewal route, notice deadline
- Seats, record limits, storage, usage units
- Overage, add-ons, support, cash schedule
Write down the number and type of seats, record or contact limits, storage, included usage units, overage, add-ons and support. Confirm which limits apply from the first invoice and which begin only after renewal. A supplier's live quote or order form, not a search result, should be the source for the price.
Products such as Salesforce Starter Suite and Dynamics 365 Sales Professional can vary by edition, billing cycle and location. Do not transfer a price from a differently localised page. When a free plan runs out, check the new paid tier's seat and record limits against its quote.
Compare the charging structure as well as the headline amount. A per-seat price and a per-contact price answer different questions, so convert mixed units before comparing totals. The pricing models comparison shows how to put different plans onto the same units.
Count the work beside the subscription
Licence charges are only one part of the estimate. Add the organisation's approved loaded hourly cost for internal work, and record the role, hours, period, overhead basis, source and owner. This keeps staff time visible as an economic cost instead of disguising it inside the supplier's price.
Budget the work around the licence
- Discovery, data cleaning and migration
- Configuration, integrations and user acceptance
- Accessibility, privacy and security review
- Training, support, change control and reporting
- Recurring admin, complaints and incident exercises
- Renewal review and export tests
- Loaded hourly cost by role, not salary
Budget discovery, data cleaning, migration, configuration, integrations and training as separate rows. Each task has its own owner and date. Use an approved loaded hourly rate rather than salary alone, and show the hours and rate inputs so a reviewer can trace the labour estimate.
Allow for work that a licence quote may omit: cleaning data before import, parallel running, training time, assurance and the cost of leaving. The hidden costs article identifies five areas a quote can leave out. Include contingency and exit rows in each case, even when a supplier's quote appears complete.
Make CRM estimate inputs traceable
For the chosen evaluation period, give every calculation line an owner and a source. Keep the currency and tax basis consistent, and make each input traceable to a dated supplier quote or an approved internal rate. The same boundaries should apply to every option, including the existing process.
- Supplier cash = quoted recurring charges + quoted one-off charges + usage or add-on charges.
- Buyer economic cost = approved loaded hourly rate by role × evidenced hours.
- Whole-life cost = supplier cash + buyer economic cost + assurance + contingency + exit cost − confirmed recoverable VAT.
The low, working and high figures show how an estimate can present different scenarios, but the licence, usage and labour-rate inputs behind these totals are not stated, so readers cannot reproduce or validate them. Replace the illustrative assumptions with your own evidence. The table separates cost excluding VAT from VAT and gross supplier cash, rather than treating those amounts as interchangeable.
Keep VAT treatment visible
HMRC's standard VAT rate guidance states that the standard VAT rate is 20% for most goods and services, but do not assume that rate or treatment applies to every quote.
HMRC guidance explains that VAT on business purchases can be reclaimed by a VAT-registered business holding valid VAT invoices and keeping records that support the claim. If taxable turnover over 12 months is below £90,000, do not assume recovery: treat the gross price as the net cost. Ask a qualified UK tax adviser to approve the VAT treatment.
Check the cash calendar as well as the total
The timing of invoices and any VAT recovery affects liquidity even where the net total is unchanged. An annual invoice paid at signing can create a larger immediate cash requirement than an accounting total suggests. Finance should assess the dated cash calendar, not just the whole-life cost.
The working-case calendar assumes signing at the start of month 1, an annual licence invoice, an implementation invoice in month 2 and a quarterly VAT return recovering VAT in month 4.
| Month | Event | Cash out | Cash back | Cumulative need |
|---|---|---|---|---|
| 1 | Annual licence invoice, including £960 VAT | £5,760 | £0 | £5,760 |
| 2 | Implementation invoice, including £600 VAT | £3,600 | £0 | £9,360 |
| 4 | VAT recovered through the quarterly return | £0 | £1,560 | £7,800 |
| 12 | Contingency and exit spend | £900 | £0 | £8,700 |
The peak requirement is £9,360 in month 2, although net supplier cost is £8,700. Add £1,400 for staff time, which is a cost but not a payment, and the total returns to the £10,100 shown in the comparison. Finance needs to see the peak requirement as well as the net figure.
Set decision checks before committing
Compare the CRM, a smaller implementation and the current-process baseline over identical periods and cost boundaries. Procurement and legal reviewers should confirm the term, price-change provisions, renewal and exit terms. A shared budget template can keep those fields together, while a dated cost comparison supports consistent inputs.
Data protection, security and accessibility owners should each approve their own controls. A lower price cannot offset a failed control or an unsafe data transfer. Reforecast when a quote expires, scope changes, a migration test fails or a new integration is introduced.
- Capture supplier legal entity, product, edition, quote date and expiry.
- List seats, record limits, storage, usage units, overage and add-ons.
- Budget discovery, data cleaning, migration, configuration, integrations and training.
- Confirm VAT treatment with a qualified UK tax adviser before assuming recovery.
- Set a reforecast trigger for quote expiry, scope change or failed migration test.